Challenge
We assisted the company with the execution of the project in Macedonia – the upgrading of the water plant in the town Probištip. The upgrade included stainless steel skid and manifold construction, pipe connections made of plastic, and a chemical dosing system, all of which had to be assembled in Macedonia. Time coordination of all contractors, as well as logistical and warehousing issues were a major problem for our client, which we could easily resolve.
About kolektor sisteh
Kolektor Sinabit and Kolektor Synatec merged to strengthen their position as the leading Slovene provider of solutions, services and equipment for automation and information flow in industry and economy.
Kolektor Sisteh’s vision is to develop technologically advanced and innovative solutions for a wider international market, including technological engineering for various branches of industry, energy, buildings and municipal infrastructure.
Their sales program further includes electronic and electrical engineering equipment of companies thay represent in Slovenia and abroad, and proper devices and systems for automation and information flow of processes, machines and devices.
Process
We have been cooperating with the Kolektor Sisteh company for many years. Based on previous positive experiences, they decided to choose us again. Once again, we provided our best certified welders of steel constructions, welders of inox pipelines and experienced installers. The client completely trusted us with the technical part of project – from the work at the workshop to the installation on the building.
Result
We made all the necessary equipment in the workshop and delivered and installed it at the facility. Because we did not have to adjust to other contractors – regarding time and space – work was carried out quickly, professionally and smoothly. We completed the installation ahead of schedule and that way the client optimized their project costs. Due to our fast, professional and high-quality performance, Kolektor Sisteh was extremely satisfied with the final result and so was their customer. Because of our quality work the customer decided to continue cooperating with the Sisteh company with new similar projects.
Client Testimonial
“Working with a team that handled everything from fabrication to installation made a huge difference. Their reliability and flexibility helped us deliver the project ahead of schedule.”
Andrej Poklar
Senior Project Manager